1. FIRE BAN lifted for KNEEHILL COUNTY
    As of 11:05 am May 20th, 2016, the fire ban for Kneehill County is no longer in effect.

    For Burn Permits, click here

    Shoulder Pulls Begin April 29

    On Friday, April 29 contract shoulder pull work will commence, starting on Twp Rd 34-4 east side of Hwy 805 heading east (NW first, then east, then south east). Approximately 2 miles of roadway will be shoulder pulled and packed per day, and Kneehill County will gravel when every 2-4 miles are completed.

    There will be traffic control along the affected roads. Traffic will be allowed to pass, however expect delays as equipment is working.

    The total Contract Shoulder Pull Project includes 90 kilometers and, weather permitting, will take approximately 30 days to complete.

    shoulder pull map 2016